Product Detail :
|
Survey, investigation, design, build, operate and transfer 90 mld capacity sewage treatment plant (stp) and 20 kld fecal sludge co-treatment facility at existing rajapur stp campus along with associate infrastructure including interception, diversion and construction of drain tapping of 07 nos. Drains, interceptor trunk sewer line (4200 mtr - open cut/trenchless method), construction of 02 nos. Sewage pumping station (sps) [1 no. At rajapur stp campus- 74 mld/56 mld capacity (ultimate year/ mid year) & 1 no. At mumfordganj sps campus -59 mld/ 39 mld capacity (ultimate year/mid year)] and 01 no. Effluent pumping station 120 mld/90 mld (ultimate year/ mid year) with allied works including rising mains (3450 mtr - open cut/ trenchless method) & effluent gravity pipe line (300 mtr -open cut/trenchless method) and effluent rising main (250 mtr) with operation and maintenance period of 15 years
|